Installation DRAINMAX tunnel

Thanks to their low weight of 38 kg, the individual tunnels can be laid effortlessly by two people. DRAINMAX tunnels are laid in rows.

If you choose "Show Video", you agree with the privacy policy of Google.
Show Video

DRAINMAX tunnel load test in the field

Note: This installation film shows a load test setup for a rainwater infiltration system with the previous DRAINMAX tunnel with separate sedimentation and filter shafts and a control shaft. Both elements are already integrated into the new DRAINMAX tunnel PP system. Instead of the white geotextile fleece, the black geotextile fabric must be laid under the trench to ensure high-pressure flushability. In general, fleece must not be laid under trenches, as its 3D structure causes it to become clogged with dirt over the years and can significantly impair the infiltration capacity of the trench. Please refer to the user guidelines for precise installation.
 

If you choose "Show Video", you agree with the privacy policy of Google.
Show Video

Installation example: rainwater infiltration

Note: This installation video shows a rainwater infiltration system with the DRAINMAX predecessor tunnel in a DIY design. For precise installation, please refer to the user guidelines.

Excavation and planning

Creation of a horizontal, level and load-bearing substrate. For drainage applications, the permeability of the compacted substrate must at least correspond to the permeability specified in the plans.

 

Laying the tunnel elements and making the pipe connections

  • Starting from the inlet, the sedimentation and filter series is usually laid first, beginning with the first dome. The first row is then completed, including the distribution element. The DRAINMAX tunnels are connected to each other with an overlap. Each row is closed off with a cap. The next rows are then laid parallel to each other at the spacing specified in the installation plan and connected to each other via the distribution element and the distribution pipes.
  • Attaching the vent pipes
  • Attaching the maintenance shaft
  • Covering with geotextile according to backfill material

Lateral backfilling of the tunnel elements

Backfill the sides and top of the tunnel elements with suitable backfill material in uniform layers on both sides.
Even compaction of the backfill layers on all sides, starting with light compaction equipment. With increasing height, heavy compaction equipment can be used.

 

When the tunnel elements are backfilled, the load-bearing capacity for the subsequent traffic surface is established.

  • The backfill material with mixed grading curve is compacted in layers over the tunnel shoulder until the required load-bearing capacity is achieved.
  • If 16/32 mm crushed stone is used, this is backfilled to 10 cm above the tunnel shoulder and covered with a geotextile separating layer. Non-cohesive soil material is further backfilled and compacted in layers until the required load-bearing capacity of 45 kN/m² is achieved.
  • Finally, the superstructure for the traffic area is constructed according to plan.

Installation options depending on application and backfill material

  1. Traffic Zone / Superstructure
  2. Substructure with compactable, material ≥ 25 cm, min. EV2 = 45 MN/m²
  3. Geotextil fleece (GT 300), Cover
  4. Gravel backfill ≥ 10 cm, above shoulder
  5. Geotextile fleece (GT 300), embankment
  6. Geotextile woven fabric (GTB 190), bottom
  7. Base and leveling layer, min. EV2 = 45 MN/m²
  8. Subsoil

  1. Traffic Zone / Superstructure
  2. Substructure with compactable, material ≥ 35 cm, min. EV2 = 45 MN/m²
  3. Geotextil fleece (GT 300), Cover
  4. Geotextile woven fabric (GTB 190), bottom
  5. Base and leveling layer, min. EV2 = 45 MN/m²
  6. Subsoil

  1. Traffic Zone / Superstructure
  2. Substructure with compactable
  3. material ≥ 25 cm, min. EV2 = 45 MN/m²
  4. Geotextil fleece (GT 300), Cover
  5. Gravel back fill ≥ 10 cm above shoulder
  6. Geotextile fleece (GT 300), embankment
  7. EPDM Liner
  8. Geotextile woven fabric (GTB 190), bottom
  9. Geotextile fleece (GT 300), bottom/embankment
  10. Base and leveling layer, min. EV2 = 45 MN/m²
  11. Subsoil

  1. Traffic Zone / Superstructure
  2. Substructure with compactable, material ≥ 35 cm, min. EV2 = 45 MN/m²
  3. Geotextil fleece (GT 300), Tunnel cover/embankment
  4. EPDM-Liner
  5. Geotextile woven fabric (GTB 190), bottom
  6. Geotextile fleece (GT 300), bottom/embankment
  7. Base and leveling layer, min. EV2 = 45 MN/m²
  8. Subsoil

Cleaning and maintenance - rinsable floor

Should dirt get into the DRAINMAX tunnel infiltration system despite pre-cleaning, it is probably the only plastic infiltration system in which the soils that are crucial for infiltration performance can be cleaned later. With conventional infiltration systems, usually only the flushing channels can be cleaned afterwards. However, the fine dirt particles get through the slots in the flushing channels and then gradually clog the bottoms of such infiltration systems. These can ultimately only be completely excavated when they have lost their infiltration performance. With the DRAINMAX tunnel infiltration system, the soil in the sedimentation and filter row can be completely flushed via the connection shaft. In critical inlet water qualities, all rows can also be equipped with an inspection and flushing shaft. This allows the entire bottom of the system to be cleaned. Since the DRAINMAX systems are always lined with a geotextile fabric and not a geotextile fleece, they can be cleaned with a high-pressure jet nozzle. The fabric also ensures that it cannot clog, unlike fleece. Therefore, only the DRAINMAX tunnel drainage system guarantees consistent infiltration performance over the long term.