Jump directly to main navigation Jump directly to content

Truck load capacity and DIBt® approval

DRAINMAX tunnels were the first tunnel technology ever to receive building approval from the German Institute for Building Technology. The long-term load-bearing capacity of the DRAINMAX system has been proven for an operating life of at least 50 years. This benefits planners, builders, fabricators and dealers alike.
The geometry of the tunnel has been used in numerous structures since ancient times. INTEWA also utilises the advantages of tunnel geometry to meet the highest stability requirements.

To achieve this, in addition to numerous installation tests in practice, extensive quality and stress tests were carried out at the Society for Materials Research and Testing Institute for Civil Engineering. These tests examine and monitor not only the material quality and short-term strength, but also the long-term strength of the component. The DIBt approval for DRAINMAX Tunnel 60 means maximum safety and quality assurance for dealers, planners, construction companies and operators.

Traffic load according to installation situation

 

DM-T/60

max. Achslast

DM-T/60

max. Überdeckung P

accessible, unpaved surface

--

0,501 - 3,00 m

Truck 12t [quivalent surface load = 6,7 kN/m²] unpaved surface8,0 t0,501,2 - 2,75 m
SLW 30 [equivalent surface load = 16.7 kN/m²] paved surface13,0 t1,00- 2,00 m
SLW 60 [equivalent surface load = 33.4 kN/m²] paved area20,0 t1,00- 1,65 m

1 only valid if the installation area is designated as frost-proof
2 in the case of unpaved surfaces, rutting must be taken into account. the monimal total coverage must not be fallen short of!